Michigan’s Construction Lien Act, 1980 PA 497, sets the notices and deadlines that determine whether a construction lien can be preserved and later enforced. The official term in the statute is “construction lien,” not “mechanic’s lien.” This article summarizes those steps in the order they usually arise. How any one deadline applies depends on the contract, the kind of project, and the facts of the work.

Who can have a construction lien

Each contractor, subcontractor, supplier, or laborer who provides an improvement to real property can have a construction lien on the interest of the owner or lessee who contracted for that improvement. The lien cannot exceed the claimant’s contract amount, less payments already made. If several liens attach to the same improvement, their total generally cannot exceed the amount the owner or lessee agreed to pay, after contract changes, less payments made under a contractor’s sworn statement or a waiver of lien. MCL 570.1107.

The notice of commencement

The Act treats a “residential structure” differently from other projects. Under MCL 570.1106(4), that term means an individual residential condominium unit or a residential building with no more than two residential units, including the land and appurtenances, in which the contracting owner or lessee is living or will live when the work is done. A larger apartment building does not qualify.

For other projects, MCL 570.1108 requires the owner or lessee who contracted for the work to record a notice of commencement with the register of deeds in each county where the property is located, before the improvement begins. One notice is enough if the work is part of a single project. The notice identifies the property, the contracting owner or lessee, the fee owner if the contracting party is a land-contract vendee or lessee, a designee, and the general contractor, if any. A copy is to be posted on the property during the work and given to the general contractor. After a written request sent by certified mail, a copy, with a blank notice of furnishing attached, is also to be provided within 10 days.

If that notice is not recorded, or is not provided after a written request, a subcontractor or supplier has until 20 days after the notice is recorded or actually furnished to provide a notice of furnishing. For a laborer, the extension runs until 30 days after the notice is recorded or provided, or until the ordinary time under section 109 expires, whichever is later.

A residential project follows MCL 570.1108a. The owner does not have to record a notice before work starts. The owner or lessee is instead to prepare and provide a notice to a contractor, subcontractor, supplier, or laborer who makes a written request, and the person who asks for it is to supply a blank form with a blank notice of furnishing attached. The form warns the homeowner to complete and return it within 10 days after the postmark. If the owner or lessee does not live at the property, a copy is to be posted there during the work. If the notice is not provided on request, a subcontractor or supplier has until 20 days after it is actually furnished to provide a notice of furnishing. For a laborer, the extension runs until 30 days after the notice is furnished, or until the ordinary section 109 time expires, whichever is later.

The notice of furnishing

A subcontractor or supplier is to provide a notice of furnishing to the designee and the general contractor named in the notice of commencement, either in person or by certified mail, within 20 days after first furnishing labor or material. If no designee is named, or if the designee has died, the notice goes to the owner or lessee named in the notice of commencement. Service by certified mail is complete on mailing. A contractor does not have to provide a notice of furnishing to preserve lien rights that arise from a contract directly with an owner or lessee. MCL 570.1109(1).

Laborers have different deadlines. A laborer is to provide a notice of furnishing within 30 days after wages were contractually due but were not paid. For unpaid fringe benefits or withholdings, the notice is due by the fifth day of the second month following the month in which those amounts were contractually due but were not paid. MCL 570.1109(2) and (3).

A late notice of furnishing by a subcontractor or supplier does not defeat a lien for work or materials furnished after the notice is served. For work done before that late notice, the lien still exists except to the extent the owner or lessee already paid the contractor under a contractor’s sworn statement or a waiver of lien. That limit does not apply to a laborer. If a laborer does not provide the required notice to the designee, the laborer’s lien for those wages, or for those fringe benefits and withholdings, is defeated. Failure to give the notice to the general contractor does not defeat the laborer’s lien, but the laborer is liable for actual damages the general contractor sustains as a result. MCL 570.1109(5) through (9).

Sworn statements

A contractor is to give the owner or lessee a sworn statement when payment is due, when the contractor requests payment, or when the owner or lessee demands one. The statement lists each subcontractor and supplier the contractor has contracted with on the improvement, and the laborers for whom wages or fringe benefits and withholdings are due but unpaid, with the amounts. A subcontractor is to give a sworn statement to the contractor when payment is due or when the subcontractor requests payment, and to the owner or lessee when the owner or lessee demands one. On a residential structure, that owner demand also depends on the receipt notices required by the statute. MCL 570.1110(1) through (4) and (6).

If a contractor records a claim of lien without first providing a sworn statement to the owner or lessee, the lien is not invalid, but the contractor is not entitled to payment and may not file a complaint, cross-claim, or counterclaim to enforce the lien until the sworn statement has been provided. If a subcontractor records a claim of lien without first providing a sworn statement demanded under section 110(2), the lien remains valid, but the subcontractor may not file an action to enforce it until the sworn statement has been provided. MCL 570.1110(9) and (10).

The 90-day claim of lien

The right to a construction lien ceases to exist unless a claim of lien is recorded with the register of deeds, in each county where the improved property is located, within 90 days after the claimant last furnished labor or material for the improvement under the claimant’s contract. The claim is valid only as to the property described in it and located in the county where it is recorded. MCL 570.1111(1).

A claim of lien by a subcontractor, supplier, or laborer is to have attached to it a proof of service of the notice of furnishing. Within 15 days after the claim is recorded, the claimant is to serve a copy of the claim of lien, and of any recorded proof of service, on the designee, either in person or by certified mail, return receipt requested. If no designee is named, or if the designee has died, service is made on the owner or lessee named in the notice of commencement. Service by certified mail is complete on mailing. MCL 570.1111(4) and (5).

The one-year action to enforce the lien

Proceedings to enforce a construction lien, and to foreclose the interests subject to it, may not be brought later than one year after the date the claim of lien was recorded. When that foreclosure action is commenced, the plaintiff is to record a notice of lis pendens with the register of deeds in the county where the property is located. The case is brought in the circuit court for that county and is equitable in nature. In an action by a contractor or subcontractor, the complaint, cross-claim, or counterclaim must show that the owner or lessee was provided a sworn statement, if one was requested or required under section 110. A lien claimant may also maintain an action on the contract from which the lien arose. MCL 570.1117 and 570.1118(1).

Attorney fees

In an action to enforce a construction lien through foreclosure, the court may allow reasonable attorney fees to a lien claimant who is the prevailing party. The court may also allow reasonable attorney fees to a prevailing defendant if it determines that the claimant’s action was vexatious. MCL 570.1118(2). The sections cited above are the starting point for reading the statute.

Published by Tishkoff PLC.

Reviewed by Tishkoff PLC attorney William G. Tishkoff.

Tishkoff PLC handles business and litigation matters for Michigan companies and owners, including construction lien, bond, defect, delay, and contract disputes. Call 734-663-4077, or visit our construction page and our litigation page. More contact options are on our contact page.

This article is general information, not legal advice for your specific situation. As always, we recommend consulting with a qualified attorney to obtain the best legal counsel on your particular situation.